Riser & PLR Installation TIMI
F23R-A and TMDR-A
Orange Delta Pte Ltd is pleased to share successful completion of the the TIMI project: offshore platforms preparation and riser plus PLR installation project.
Our scope of work included onshore (preparatory):
– Project Management
– Method and Structural Engineering
– Provision of Tooling, Equipment and Personnel
– Equipment Testing in Compliance with Shell
– Training & Certification of Personnel Offshore
– Mobilization and Operational Management
– PTW training
Scope of Work (offshore):
– Mobilization and Operational Management
– PTW application
– Erect Scaffolding and Rope Access
– Equipment Installation (Genset, HPU, Compressor, Winches, Chain blocks)
– Riser Guard Lifting, before vessel arrival
– Riser Pull-In
– Riser Clamp Installation
– Riser Guard Lowering and securing
– PLR Installation (2 platforms)
Orange Delta have installed over 20 risers along with their associated PLR’s, clamps
and piping – over 18 platforms at offshore Brunei and Sarawak Malaysia. We are the
Contractor to deliver complete engineering and project management, fabrication,
supply of equipment within our fleet and the skilled personnel to execute the Platform
Preparation Services.
The preparatory work includes the methods engineering and
work packages, permits to work, rigging design; identification and logistics
arrangement of our fleet of equipment and personnel from various disciplines: Rope
Access, Rigging, Welding, Mechanics, Scaffolding.
We provide complete set of ex-rated offshore equipment for the platform preparation
services – pull-in system (hydraulic/ air winch along with power supply), scaffolding
materials including lighting, suitably designed rigging and installation aids, welding/
NDT/ coating machines, personal and centralized gas detectors, tensioning/ torquing
tools within container(s).